Title:
|
Consideration of approval of contract with Sunland Asphalt & Construction for the application of fog seal to select city streets. The work would be through the 1 Government Procurement Alliance Cooperative Contract No. 22-15P-04 in the amount of $321,774.89 plus a 10% contingency for unforeseen change orders for total project cost not to exceed $353,922.37. Work is planned within the March-April 2025 time frame.
|