Title:
|
Consideration of approval of award of contract to Sunland Asphalt for the reconstruction of Ironwood Drive from Lost Dutchman Boulevard to McKellips Road. The work would be through the 1 Government Procurement Alliance cooperative contract No. 17-16P-05 in the amount of $595,344.00 plus a 10% contingency for unforeseen change orders in the amount of $59,534.40 for a total project cost not to exceed $654,878.40. Work will result in a new paved surface, street striping and bike lanes for this portion of Ironwood Drive. Work is planned for this fall or winter of 2019, depending on scheduling and weather conditions.
|